Texas Renewable Energy Keeps Growing: Both Austin and ERCOT Showing it Can Be Done

Ok I’ve written about this before but the pace is getting to be mind-boggling. Every month, ERCOT releases its Monthly Status System Planning Report and the amount of proposed generation keeps growing. And in particular what appears to be winning is wind power, and increasingly solar. The February 2014 Monthly Status Report shows that ERCOT is currently tracking 219 proposed projects totaling over 55,300 MWs, about half – 26,700 MWs in all — of which is wind. The latest to sign what is known as a Generation Interconnection Agreement with the local transmission company is the Briscoe Wind Farm, a 300 MW facility located in West Texas. Just earlier this month we announced that Austin Energy had negotiated a cheap wind deal with Lincoln Renewable for 300 MWs in Castro County.

Here are the latest numbers from ERCOT.

Confidential Projects Projects under Study Projects with Signed Agreement Total
Natural Gas 3,544 11,437 9,521 24,502
Coal 0 30 240 270
Wind 5,538 12,777 8,413 26,728
Solar 1,335 1,414 198 2,947
Storage 0 874 0 874
Nuclear 0 0 0 0
Petroleum Coke 0 0 0 0
Total 10,417 26,532 18,372 55,321

What is pretty interesting is the geographic distribution of these projects. If you look at ERCOT’s five traditional load zones — Panhandle, West Texas, North Zone, South Zone and Coastal Zone, future natural gas projects dominate in the South and North Zone — where wind and solar resources are just not as strong. But from the Coastal Zone — where gas and wind split the pie — to West Texas and especially the Panhandle, wind and increasingly solar beat out gas projects.

Coal you might ask? Two projects – a tiny 30 MW proposed project in Milam County and the long-awaited IGCC project by Summit in Ector County, which has been delayed three times, and is currently scheduled for 2018.. maybe. Petroleum Coke, like those proposed Las Brisas and White Stallion projects that SIerra Club fought?  Dead. none. What about nuclear? Didn’t NRG and Luminant promise to build us new reactors? Dead.

In fact, other than gas, wind and solar, the only projects are three proposed storage facilities which could revolutionize the use of renewable energy, making it dispatchable just like gas.

Image

Webberville Project — three times more expensive than the new one they are talking about.

Now back to Austin Energy. While two weeks ago we told you about a deal to purchase wind at a bargain rate of $26 to $36 per MWh that City Council recently approved — a price rivaling what we pay for our dirty coal power — this Thursday Austin Energy will be proposing to City Council that they authorize negotiations over two utility-scale solar plants to be constructed by SunEdison. While the exact price can not be revealed, Austin Energy is reporting that it is between $45 and $55 per MWh, making it the cheapest solar deal in the country. The two plants will total up to 150 MWs of capacity, and be located in West Texas. If these deals come to fruition, Austin Energy would not only meet its 35% renewable energy commitment four years early by the time the plants come online in 2016, but even its 200 MW solar goal. With the Local Solar Advisory Committee recommending that Austin Energy double its goal to 400 MWs by 2020, Austin Energy’s initial negative reaction — based on a belief that solar would cost more in the $80 to $100 per MWh range — now seems well.. so last year. In fact, Austin Energy reports that they had over 125 proposals for utility-scale solar from 66 separate projects, and $100 per MWh was the very highest they got. In fact, most were in the $60 dollar range. Remember in 2009, we negotiated a deal for 30 MWs of solar for around $165 per MWh. So that means for Austin Energy solar energy prices got chopped by some 70% between 2010 and 2016 when the latest solar projects get built.

Folks, the news for renewable energy in Texas just keeps getting better. Cyrus Reed, Conservation Director, Lone Star Chapter

Victory! Austin City Council Votes 6-0 In Favor of Generation Plan Task Force

Screen Shot 2014-03-06 at 12.56.57 PM

FOR IMMEDIATE RELEASE:

March 6, 2014

Contact: Dave Cortez, David.Cortez@SierraClub.Org, 512-736-7600

Austin City Council Votes to Create Austin Energy Task Force

AUSTIN, TX – Today, in a 6-0 vote, city council members voted to create the Austin Energy Resource Generation Task Force as part of the 2014 update process to the city’s existing energy plan.

The task force is directed to provide recommendations to council members for how Austin Energy should meet existing goals for renewable energy by 2020, as well as opportunities for strengthening and expanding those goals through 2024. Task force members will include one member from the Electric Utilities Commission and one from the Resource Management Commission, as well as seven other members appointed by city council.

Sierra Club Beyond Coal Organizer David Cortez
issued the following statement in response:

“Public participation is always a win-win in our book. Today, the people of Austin and Central Texas communities impacted by climate disruption won a major procedural victory for clean energy, transparency and good governance. This task force will provide environmental, low-income, renewable energy and industry stakeholders their best opportunity to review Austin Energy’s approach and set a clear path for making Austin a leader in the clean energy economy.

Austin Energy ratepayers have made it clear that they want this process to expand our clean energy goals, phase out our over-reliance on dirty coal and fracked gas, as well as preserve our affordability targets. We see this task force as the best way to ensure those demands are met.

The Sierra Club and our 4,500 Central Texas members and supporters applaud City Council for their leadership in making this process more accessible to all Austin Energy ratepayers.”

###

 

Austin City Councils hears from Austin Energy on new proposed 300 MW wind contract: 35% renewable energy by 2016

This morning, Austin Energy is slated to present to their bosses — Austin City Council — on a proposed contract that would secure an additional 300 MWs of wind energy from West Texas near Lubbock. The proposed contract would cost an estimated $31 million per year in energy purchases from Lincoln Renewable Energy over 18 years and more importantly if approved would meet Austin Energy’s renewable energy of 35% by 2020 four years early. The cost of the wind is priced in the $26 to $36 per MWh range, which is typically cheaper than the price of electricity generated by gas and almost on par with the cost from the dirty Fayette Coal plant. And this price is guaranteed over 18 years. And if it breaks, we don’t have to pay for it. So no operations and maintenance required by us ratepayers. 

 

Sierra Club is supportive of this and other contracts with renewable energy companies, and the word on the street is that Austin Energy will be taking another contract soon for a large solar energy plant or two in the coming months. Will all this activity, one does wonder however why Austin Energy has consistently said we don’t need to reassess our renewable energy goals? While one should certainly celebrate reaching a goal — I mean this beat’s California’s 33% goal set a number of years ago — why not take advantage of good financing and good projects to shoot for a higher goal — say 50% by 2020? While it is true that the vaunted production tax credit granted to wind developers ran out in 2013, any project — including this one — that began construction in 2013 still qualifies, and ERCOT’s interconnection records show us there are more than 5,000 MWs of wind projects being developed in 2014 and 2015 that likely would meet the PTC requirements. So let’s grab up these contracts while we can and wean ourselves off the need for coal, gas and buying off the market. Reaching out and securing  these contracts doesn’t mean we don’t need coal and gas today, but it does mean we can envision a future where we won’t need them as much.. if at all. So keep it coming Austin Energy! We can not only reach our goals, but set more ambitious ones!

 

Cyrus Reed, Conservation Director

Austin’s 10-Year Energy Plan: Ramp Up Renewables, or Double Down on Fossil Fuels?

Stop Dirty Coal Rally, Austin, Texas

***MEDIA ADVISORY FOR TUESDAY, FEBRUARY 25th***

FOR PLANNING PURPOSES

Contact:
Dave Cortez, Sierra Club Beyond Coal,
David.Cortez@SierraClub.Org, 512-736-7600
Kaiba White, Public Citizen, Kwhite@citizen.org, 607-339-9854

Austin Energy Ratepayers Rally to Expand Affordable Renewable Energy Goals in Energy Plan Update 

WHAT: Clean Energy Rally Following First Austin Energy Stakeholder Meeting

WHERE: Front Lawn, Austin Energy HQ, Town Lake Center, 721 Barton Springs Road
WHEN: Tuesday, February 25th at 12:15 pm
(following the conclusion of Austin Energy’s first stakeholder meeting)

WHO:  Hosted by the Sierra Club Beyond Coal Campaign and Public Citizen

VISUALS FOR CAMERAS: We’ll have 30 Austin Energy Ratepayers wearing yellow shirts and holding clean energy signs next to a large solar panel. A coal lobbyist clad in a suit and a large black smokestack costume will be doing all he can to remove the solar panel from the rally. Parents and children will also be in attendance to highlight the need to plan for clean future for our kids.
.
Coal Monster
.
FULL SCHEDULE OF AE STAKEHOLDER MEETINGS: 

Tuesday, Feb. 25, 2014 – 10 a.m. to Noon
Tuesday, Feb. 25, 2014 – 6 p.m. to 8 p.m.
Thursday, Feb. 27, 2014 – 1 p.m. to 3 p.m.

Austin Energy Headquarters
Town Lake Cntr
721 Barton Springs Road
First floor assembly room

AUSTIN – On Tuesday, February 25th at 12:15 PM CT, dozens of yellow-shirt clad Austinities will rally in support of clean energy and moving beyond fossil fuels outside of Austin Energy headquarters following the first of three stakeholder input meetings on the proposed 10-year update to the Austin Energy Resource, Generation, and Climate Protection Plan.

Austin Energy has given no indication that it will incorporate City Council’s recommendation that the solar energy goal be expanded to 400 megawatts by 2020 – enough to power about 50,000 homes. Nor has it suggested increasing the overall renewable energy goal, despite the fact that it’s already has contracts to meeting the current goal 4 years early. Instead, the utility is proposing to keep the Fayette coal plant running through 2025 and to build an additional 800 megawatt fracked gas plant.

The rally is hosted by the Sierra Club Beyond Coal Campaign and Public Citizen.

Latest ERCOT planning report again points to gains for wind and solar

Every month, ERCOT — the Electric Reliability Council of Texas — releases a monthly planning report which reviews existing and new generation resources, asynchronous tie interconnection, transmission planning and other notable activiites. Once again, the December  2013 System Planning report showed significant gains for wind. Thus, several new wind projects went on-line in December, bringing the total amount of wind within ERCOT to 11,255 MWs, including 2,775 MW in the South zone, which is essentially coastal wind resources which tend to blow more consistently during the days. In addition, three new wind projects signed interconnection agreements in West Texas.

According to their latest summary of Generation Interconnection Requests, some 15,301 additional MWs of generation have signed interconnection agreements. Of this, 7,484 MWs is gas generation, and 7,447 is wind generation. Some 130 MWs of solar projects have confirmed interconnection agreements with transmission companies. Only one coal project — the Summit carbon-capture project near Odessa — has a signed interconnection agreement. In addition, some 35,000 MWs of additional generation is in the study phase — looking to see if going forward makes sense. Of this, about 15,000 MWs is gas, and 17,000 MWs is wind, with another 2,700 MWs of solar in the development queue. There are no biomass, nuclear or coal plants, but there are 875 MWs of storage being considered. The planning report shows that the future of electricity in Texas will be some combination of wind, solar, storage and yes, some newer gas units. Coal and nuclear appear to have no future. The Sierra Club will continue to work to set the rules so that the cleanest resources — wind, storage, solar and of course energy efficiency and demand response – can compete and ultimately win. According to our electric grid operator, those resources are already winning!

The report also lists three “ties” — that is devices that allow the ERCOT grid to interconnect with either the Western, Eastern or Mexican electric grids. While a small interconnection will go into effect this year — known as Railroad — there are two major projects being considered which would allow significant renewable resources to move out of Texas to other markets, or alternatively, other markets into Texas’s.  The Southern Cross HVDC — an interconnection with the Eastern SERC grid — could move massive amounts of wind — up to 3,000 MWs — in Texas and Oklahoma (and solar too) into the Southeast, while the Tres Amigas project in eastern New Mexico could allow 1500 MWs of Texas wind into New Mexico, Arizona and California (and perhaps some solar from those states into Texas). While these projects are still undergoing studies, they could revolutionize the use of renewables throughout the Southern US. Sierra Club will also be watching these projects, and is generally supportive, though the location of transmission lines and wind development must be sited appropriately to avoid any special habitats or special places. Onward!